Europe Cement Investment and Trade S.A. (Poland) v. Republic of Turkey

 
Counsel:

Mannheimer Swartling Advokatbyrå (K. Hóber, J. Ragnwaldh & N. Eliasson) v. Freshfields Bruckhaus Deringer (J. Paulsson, L. Reed & B. King) and Cosar Avukatlik Bürosu (Aydin Cosar, U. Cosar & Arzu Cosar)
 

Case registered:

06.03.2007
 

Forum & reference:

ICSID Case n°. ARB(AF)/07/2
 

Arbitrators:

Donald McRae (Chair); Julian D M Lew QC; Laurent Lévy
 

Subject matter:

Electricity concessions
 

Status of proceeding:

Pending

13.09.2007 - Tribunal constituted
16.11.2007 - Parties file a joint submission on procedural matters
21.11.2007 - Tribunal holds a first session with the parties by telephone conference
19.12.2007 - Respondent files requests for the suspension of the proceeding, for production of documents, and for provisional measures
                        On the same day, the Claimant files a request for provisional measures
30.12.2007 - Claimant files observations on the Respondent's requests filed on 19.12.2007

10.01.2008 - Respondent files observations on the Claimant's request for provisional measures
22.01.2008 - Tribunal issues Procedural Order No. 1 concerning the parties' respective requests for provisional measures
13.03.2008 - Claimant files a further request for provisional measures, and requests an extension to submit its memorial
20.03.2008 - Respondent files observations on the Claimant's requests of 13.03.2008
02.04.2008 - Claimant files a reply on its requests of 13.03.2008
14.04.2008 - Tribunal issues Procedural Order No. 2 concerning the procedural calendar
15.05.2008 - Claimant files a memorial on jurisdiction and admissibility
22.05.2008 - Parties file certain renewed applications
25.05.2008 - Tribunal holds a hearing on the parties' renewed applications in Paris
29.05.2008 - Tribunal issues Procedural Order No. 3 concerning the Respondent's renewed applications
05.06.2008 - Tribunal issues Procedural Order No. 4 concerning the Claimant's renewed applications
23.06.2008 - Claimant files observations on Respondent's request for the production of documents
30.06.2008 - Respondent files a reply to Claimant's observations
23.07.2008 - Tribunal issues Procedural Order No. 5 concerning the procedural calendar
11.09.2008 - Tribunal issues Procedural Order No. 6 concerning the procedural calendar
12.09.2008 - Tribunal issues Procedural Order No. 7 concerning the procedural calendar
17.11.2008 - Tribunal issues Procedural Order No. 8 concerning the procedural calendar
03.12.2008 - Tribunal issues Procedural Order No. 9 concerning the procedural calendar
04.12.2008 - Claimant files a request for the discontinuance of the proceeding
16.12.2008 - Respondent objects to the Claimant's request for the discontinuance of the proceeding
23.12.2008 - Tribunal issues Procedural Order No. 10 concerning the continuation of the proceeding

13.08.2009 - Award rendered
 

Claim:

USD 3.8 billion (www.globalarbitrationreview.com)
 

Award:

Award (click to download)