The following is a list of investor-state dispute settlement cases. This information was compiled by the Energy Charter Secretariat and is updated regularly.
Please note that there is no requirement that such disputes be notified to the Secretariat, nor is the Secretariat involved in the administration of the investor-state dispute settlement procedure. The information below was compiled from various public sources, and includes links to publicly available documents; while the Secretariat has made efforts to ensure that this information is reliable, its accuracy and completeness cannot be guaranteed.
Counsel: Allen & Overy (S. Jagusch & J. Gill) v. information not publicly available
Case registered: 25.04.2001
Forum & reference: ICSID Case No. ARB/01/4
Arbitrators: Allan Philip (chair); Francisco Orrego Vicuña; Prosper Weil
Subject matter: Electricity sale agreement
Status of proceeding: Settlement agreed by the parties and proceeding discontinued at their request (3 January 2002)
Claim: Information not publicly available
Award: N/A
Counsel: Hellström & Partners Adv. (J. Wetterfors & P. Winnberg) v. Setterwalls Adv. (F. Wennerholm & P. Törnquist) Grunte & Cers, Riga (G. Cers)
Case registered: 11.12.2001
Forum & reference: Arbitration Institute of the SCC - Case No 118/2001
Arbitrators: Bjørn Haug (chair); Rolf A. Schütze; Johan Gernandt
Subject matter: Electricity sale agreement
Status of proceeding: Award rendered on 16.12.2003
Claim: 7,097,680 Lats (information from the award)
Award: Award (click to download)
Counsel: Shearman & Sterling LLP (E. Gaillard & J. Savage); V. Colaiuta ("Avocat à la Cour" - for the phase on the merits up to May 2007); Nixon Peabody LLP (F.H. Penski - hearing on the merits) v. Bulgarian Ministry of Finance (I. Kondov); White & Case LLP (P. Friedland - New-York; C.B. Lamm; A. Cohen Smutny - Washington DC); Tomov & Tomov (L. Tomov)
Case registered: 19.08.2003
Forum & reference: ICSID Case No. ARB/03/24
Arbitrators: Carl F. Salans (chair); Albert Jan van den Berg; V.V. Veeder
Subject matter: Oil refinery investment
Status of proceeding: Award rendered on 27.08.2008
28.10.2005 - Decision on jurisdiction (click to download)
Claim: USD 300 million (Shearman & Sterling website)
Award: Award (click to dowload)
Revision proceeding
27.09.2011 - Case registered
03.10.2011 - Tribunal reconstituted (Carl F. Salans (chair); Albert Jan van den Berg; V.V. Veeder)
Status of revision proceeding: The Tribunal issues a procedural order for the discontinuance of the proceeding for lack of payment of the required advances, pursuant to ICSID Administrative and Financial Regulation 14(3)(d) on 09.07.2012
Counsel: Setterwalls Adv. (F. Wennerholm & J. Sidklev) v. Leboeuf, Lamb, Green & McRae (E. Claes - Brussels; J.T. Corrigan & N. Aldashec - Bishkek)
Case registered: 01.09.2003
Forum & reference: Arbitration Institute of the SCC - Case No 126/2003
Arbitrators: former Justice Hans Danelius (chair), Jeroen Smets, Professor Ove Bring
Subject matter: Gas delivery contract
Status of proceeding:
Award rendered on 29.03.2005
Application for setting aside of award rejected by Svea Court of Appeal on 13.04.2006
Claim: USD 4,084,652.2 (information from the award)
Award: Award (click to download)
Judgment (click to download)
Counsel: Lovells (A.R. Marshall & J. Reynolds), James Crawford SC & Simon Olleson v. Milbank, Tweed, Hadley & McCloy LLP (M.D. Nolan & E. Baldwin)
Case registered: 18.03.2004
Forum & reference: ICSID Case No. ARB/04/10
Arbitrators: Marc Lalonde QC (chair); Jan Paulsson; Sir Anthony Mason
Subject matter: Thermal energy project, dispute relating to boiler rehabilitation
Status of proceeding: Settlement agreed by the parties and proceeding discontinued at their request
(Order taking note of the discontinuance pursuant to Arbitration Rule 43(1) issued by the Tribunal on 13.03.2006)
Claim: Information not publicly available
Award: N/A
Counsel: Shearman & Sterling (E. Gaillard, Y. Banifatemi, P. Pinsolle) v. Cleary Gottlieb (R.T. Greig, C. Annacker)
Case registered: 03.02.2005
Forum & reference: Ad hoc UNCITRAL Arbitration Rules; arbitration administered by the Permanent Court of Arbitration (PCA) in The Hague
Arbitrators: L. Yves Fortier (chair); Charles Poncet (replacing Daniel Price); Stephen Schwebel
Subject matter: Discriminatory measures and expropriation of investments
Status of proceeding: Pending
30.11.2009 - Interim Award on Jurisdiction and Admissibility rendered (click to download)
Claim: USD 100 billion (total amount of compensation sought for disputes 6, 7, 8 - www.globalarbitrationreview.com)
Award: N/A
Counsel: Shearman & Sterling (E. Gaillard, Y. Banifatemi, P. Pinsolle) v. Cleary Gottlieb (R.T. Greig, C. Annacker)
Case registered: 03.02.2005
Forum & reference: Ad hoc UNCITRAL Arbitration Rules; arbitration administered by the Permanent Court of Arbitration (PCA) in The Hague
Arbitrators: L. Yves Fortier (chair); Charles Poncet (replacing Daniel Price); Stephen Schwebel
Subject matter: Discriminatory measures and expropriation of investments
Status of proceeding: Pending
30.11.2009 - Interim Award on Jurisdiction and Admissibility rendered (click to download)
Claim: USD 100 billion (total amount of compensation sought for disputes 6, 7, 8 - www.globalarbitrationreview.com)
Award: N/A
Counsel: Shearman & Sterling (E. Gaillard, Y. Banifatemi, P. Pinsolle) v. Cleary Gottlieb (R.T. Greig, C. Annacker)
Case registered: 03.02.2005
Forum & reference: Ad hoc UNCITRAL Arbitration Rules; arbitration administered by the Permanent Court of Arbitration (PCA) in The Hague
Arbitrators: L. Yves Fortier (chair); Charles Poncet (replacing Daniel Price); Stephen Schwebel
Subject matter: Discriminatory measures and expropriation of investments
Status of proceeding: Pending
30.11.2009 - Interim Award on Jurisdiction and Admissibility rendered (click to download)
Claim: USD 100 billion (total amount of compensation sought for disputes 6, 7, 8 - www.globalarbitrationreview.com)
Award: N/A
Counsel: Skadden, Arps, Slate, Meagher & Flom (UK) LLP (K. Nairn & D. Herlihy) v. DLA Piper (C. Salomon & M. Saunders)
Case registered: 03.10.2005
Forum & reference: ICSID Case No. ARB/05/18
Arbitrators: L. Yves Fortier (chair); Francisco Orrego Vicuña; Vaughan Lowe (appointed following the passing away of Arthur Watts)
Subject matter: Oil and gas distribution enterprise
Status of proceeding: Award rendered on 03.03.2010
27.02.2006 - Tribunal constituted
15-16.01.2007 - Tribunal holds a first hearing on jurisdiction in London
06.07.2007 - Decision on jurisdiction (click to download)
10.01.2009-19.01.2009 - Tribunal holds a hearing on the merits in London
03.03.2010 - Award rendered
Claim: USD 350 million (DLA Piper website)
Award: Award (click to download)
Annulment proceeding
16.07.2010 - Application for annulment registered
11.08.2010 - Ad hoc Committee constituted (Dominique Hascher (Chair); Cecil W.M. Abraham; Karl-Heinz Böckstiegel)
Status of proceeding: The ad hoc Committee issues an order taking note of the discontinuance of the proceeding pursuant to ICSID Arbitration Rules 53 and 43(1) on 12.12.2011
Revision proceeding
21.01.2011 - Case registered
04.02.2011 - Tribunal reconstituted (L. Yves Fortier (Chair), Vaughan Lowe, Francisco Orrego Vicuña)
Status of revision proceeding: The Tribunal issues a procedural order taking note of the discontinuance of the proceedings pursuant to ICSID Arbitration Rules 53 and 43(1) on 21.12.2011
See also report in Investment Arbitration Reporter at www.iareporter.com/articles/20101015
Counsel: Mannheimer Swartling (K. Hóber) & Svahnström (S. Svahnström) v. Grischenko & Partners (S. Voitovich, D. Grischenko and D. Shemelin) and Proxen & Partners (A. Alekseyev and O. Shevchuk)
Case registered: 24.11.2005
Forum & reference: Arbitration Institute of the SCC
Arbitrators: Bernardo Cremades (chair), Per Runeland, Christer Söderlund
Subject matter: Nuclear power plant (dispute arising out of the bankruptcy of a nuclear power plant and default under contracts to provide services in relation to high voltage electrical equipment used in Zaporizhya power plant in Ukraine)
Status of proceeding: Award rendered on 26.03.2008
Claim: EUR 14,999,194 for losses and USD 594,902 for costs (information from the award)
Award: Award (click to download)
Counsel: Hunton & Williams (R.W. Hawkins & D.D. Cors, Washington, D.C.; S.M. Sayers & T.J. Cawley of McLean, Va.) v. Allen & Overy (S. Jagusch, M. Levy, A. Sinclair & M. Jain - London; L. Gouiffès - Paris)
Case registered: 28.12.2005
Forum & reference: ICSID Case No. ARB/05/24
Arbitrators: David A. R. Williams (chair); Judge Charles N. Brower; Jan Paulsson
Subject matter: Nuclear power plant
Status of proceeding: Pending
20.04.2006 - Tribunal constituted
03.07.2006 - Tribunal holds a first session in London
05-16.05.2008 - Hearing on jurisdiction and merits in Paris
12.06.2009 - Decision on the Treaty interpretation issue and Individual Opinion (click to download)
Claim: Euro 31.7 Million (statement from Croatia's Ministry of Economy)
Award: N/A
Counsel: Crowell & Moring LLP (S.H. Newberger, D. Contratto) & A.L. Demetriades, Barrister (Cyprus) v. Freshfields Bruckhaus Deringer LLP (L. Reed, D.B. King and N. Rubins - New York; J. Paulsson - Paris) and Coşar Avukatlik Bürosu (A. Coşar, A. Coşar, U. Coşar)
Case registered: 19.04.2006
Forum & reference: ICSID Case No. ARB/06/8
Arbitrators: Michael Hwang (chair), Henri C. Alvarez and Sir Franklin Berman Q.C.
Subject matter: Electricity generation and distribution concessions (expropriation)
Status of proceeding: Final Award rendered on 02.09.2011
18.12.2006 - Tribunal constituted
12.02.2007 - Tribunal holds a first session in New York
28-29.04.2008 - Tribunal holds a hearing on the parties' request in Washington, D.C.
23.06.2008 - Tribunal issues a detailed decision on preliminary issues
02.09.2011 - Final Award rendered
Claim: USD 10 billion (claim announced 23.02.2006 www.crowell.com)
Award: Award (click to download)
Annulment proceeding
20.12.2012 - Case registered
14.02.2012 - Ad hoc Committee constituted (Andrés Rigo Sureda (Chair); Hans Danelius; Eduardo Silva Romero)
Status of annulment proceeding: Pending
Counsel: McDermott Will & Emery UK LLP (J. Blanch & A. Moody) v. Allen & Overy (S. Jagusch, J. Gill & A. Sinclair - London; L. Gouiffès - Paris)
Case registered: 30.08.2006
Forum & reference: ICSID Case No. ARB/06/15
Arbitrators: Florentino P. Feliciano (chair - appointed following the passing away of Arthur Watts), Professor Christopher Greenwood QC CMG, Judge Charles N. Brower
Subject matter: Oil and gas distribution, trade, storage and transportation enterprises
Status of proceeding: Award rendered on 08.09.2009
18.01.2007 - Tribunal is constituted
02.04.2007 - Tribunal holds its first session in London
30.06-01.07.2008 - Tribunal holds a hearing on jurisdiction in London
07.01.2009 - Tribunal issues a procedural order concerning the Respondent's request for the discontinuance of the proceeding of 31.12.2008
08.09.2009 - Award rendered
Claim: Information not publicly available
Award: Award (click to download)
Counsel: Lovells (M. Davison & J. Reynolds); Yazici (M. Yazici) v. Latham & Watkins LLP (R. Volterra & S. Seeleman-Eggebert)
Case registered: 16.10.2006
Forum & reference: ICSID Case No. ARB/06/16
Arbitrators: Vaughan Lowe (chair); Peter Galbraith; Brigitte Stern
Subject matter: Electricity concession
Status of proceeding: 28.09.2009 - Settlement agreed to by the parties and recorded in the form of an award
Claim: Information not publicly available
Award: Settlement award (not publicly available)
Counsel: Mannheimer Swartling Advokatbyrå (K. Hóber, J. Ragnwaldh & N. Eliasson) v. Freshfields Bruckhaus Deringer (J. Paulsson, L. Reed & B. King) and Cosar Avukatlik Bürosu (Aydin Cosar, U. Cosar & Arzu Cosar)
Case registered: 16.11.2006
Forum & reference: ICSID Case No. ARB(AF)/06/2
Arbitrators: Pierre Tercier (Chair), Marc Lalonde QC, Christopher Thomas
Subject matter: Electricity concessions
Status of proceeding: Award rendered on 17.09.2009
11.05.2007 - Tribunal constituted
23.08.2007 - Tribunal holds a first session in Paris
26.05.2008 - Tribunal holds a hearing on the parties' renewed applications in Paris
30.07.2008 - Tribunal issues a procedural order concerning the procedural calendar
22.01.2009 - Tribunal issues a procedural order deciding to deal with the objections to jurisdiction as a preliminary matter; as a result the proceeding on the merits is suspended
17.09.2009 - Award rendered
Claim: USD 4.6 billion (www.globalarbitrationreview.com)
Award: Award (click to download)
Counsel: Mannheimer Swartling Advokatbyrå (K. Hóber, J. Ragnwaldh & N. Eliasson) v. Freshfields Bruckhaus Deringer (J. Paulsson, L. Reed & B. King) and Cosar Avukatlik Bürosu (Aydin Cosar, U. Cosar & Arzu Cosar)
Case registered: 06.03.2007
Forum & reference: ICSID Case No. ARB(AF)/07/2
Arbitrators: Donald McRae (Chair); Julian D M Lew QC; Laurent Lévy
Subject matter: Electricity concessions
Status of proceeding: Award rendered on 13.08.2009
13.09.2007 - Tribunal constituted
21.11.2007 - Tribunal holds a first session with the parties by telephone conference
25.05.2008 - Tribunal holds a hearing on the parties' renewed applications in Paris
23.07.2008 - Tribunal issues a procedural order concerning the procedural calendar
23.12.2008 - Tribunal issues a procedural order concerning the continuation of the proceeding
13.08.2009 - Award rendered
Claim: USD 3.8 billion (www.globalarbitrationreview.com)
Award: Award (click to download)
Counsel: Clifford Chance (A. Sheppard, A. Panayides & I. Suarez Anzorena) v. Reed Smith LLP (D. Warne & B. Paisley) and 3 Verulam Buildings (A. Malek QC & C. Harris)
Case registered: 16.07.2007
Forum & reference: ICSID Case No. ARB/07/14
Arbitrators: Karl-Heinz Böckstiegel, Kaj Hóber and James R. Crawford
Subject matter: Exploration and extraction of hydrocarbons
Status of proceeding: Award rendered on 22.06.2010
24.01.2008 - Tribunal constituted
02.04.2008 - Tribunal holds a first session in London
15.10.2008 - Tribunal issues a procedural order concerning the procedural calendar
22.06.2010 - Award rendered
Claim: Information not publicly available
Award: Information not publicly available
Counsel: Clifford Chance LLP (J. Beechey, A. Sheppard - London & Z. Faludi - Budapest) v. Arnold & Porter LLP (J. Engelmayer Kalicki - Washington, D.C., T. Frazer - London, L. Gyselen - Brussels) & Dr. J. Katona
Case registered: 13.08.2007
Forum & reference: ICSID Case No.ARB/07/19
Arbitrators: V.V. Veeder (Chair); Gabrielle Kaufmann-Kohler; Brigitte Stern
Subject matter: Electricity generation: declarations of unlawful expropriation, and breaches of Articles 10(1) and 10(7). Claimant also asks for the determination of compensation in a further phase of the arbitral proceedings (see paragraph 1.47 of the Tribunal's decision dated 30.11.2012)
Status of proceeding: Pending
05.12.2007 - Tribunal constituted
15.05.2008 - Tribunal holds a first session in London
03.09.2008 - ICSID receives a petition for amicus curiae participation from the European Commission
28.04.2009 - Tribunal issues a procedural order concerning the application of a non-disputing party to file a written submission pursuant to ICSID Arbitration Rule 37(2)
09-17.02.2010 - Tribunal holds a hearing on the merits in Washington, D.C.
30.11.2012 - Tribunal issues a decision on jurisdiction, applicable law and liability (click to download)
Claim: Information not publicly available
Award: N/A
Counsel: Allen & Overy (S. Jagusch, R. Farnhill & J. Sullivan) v. Arnold & Porter LLP (J. Engelmayer Kalicki - Washington, D.C., T. Frazer - London, L. Gyselen - Brussels) & Dr. J. Katona
Case registered: 13.08.2007
Forum & reference: ICSID Case No.ARB/07/22
Arbitrators: Claus von Wobeser (Chair); J. William Rowley; Brigitte Stern
Subject matter: Electricity generation
Status of proceeding: Award rendered on 23.09.2010
20.11.2007 - Tribunal constituted
09.01.2008 - Tribunal holds a first session in London
03.09.2008 - ICSID receives a petition for amicus curiae participation
26.11.2008 - Tribunal issues a procedural order concerning the filing of an amicus curiae written submission pursuant to ICSID Arbitration Rule 37(2)
23.09.2010 - Award rendered
Claim: Not quantified; allegations of breach of obligations under Articles 10(1), 10(7) and 13 of the ECT
Award: Award (click to download)
Annulment proceeding
28.01.2011 - Case registered
21.03.2011 - Ad hoc Committee constituted (Bernard Hanotiou (Chair); Rolf Knieper; Abdulqawi Ahmed Yusuf)
29.06.2012 - Ad hoc Committee issued its decision
Ad hoc Committee's decision: Decision (click to download)
Counsel: Prof. A. Amkan & Dr F. Schwank (for jurisdictional and liability phase); Martin, Lubitz & Hyman LLC (J. F. English) (for final phase) v. information not publicly available
Case registered: 30.05.2008
Forum & reference: Arbitration Institute of the SCC - case No V (064/2008)
Arbitrators: Jeffrey M. Hertzfeld (Chair); Richard Happ; Prof. Ivan S. Zykin
Subject matter: Hydrocarbon exploration licences
Status of proceeding: Final award rendered on 08.06.2010
02.09.2009 - Partial award on jurisdiction and liability rendered (click to download)
Claim: USD 227 million plus specific performance
Award: Award (click to download)
Counsel: Shearman & Sterling LLP (P. Pinsolle & Y. Banifatemi) v. Clifford Chance LLP (A. Sheppard & B. Kruzewski) and Public Prosecutor's office (R. Zajdler)
Case registered: 24.07.2008
Forum & reference: Arbitration Institute of the SCC
Arbitrators: Pierre Tercier (Chair); Albert Jan van den Berg; Vaughan Lowe QC
Subject matter: Mandatory fuel reserves
Status of proceeding: Final award rendered in December 2011
Tribunal constituted (announced on 22.01.2009 at www.iareporter.com)
Claimant announces that, on 17.12.2009, the Tribunal rejected the jurisdictional objection raised by the Respondent (Mercuria website)
Final award rendered in December 2011, rejecting Mercuria's claims
(reported by the Investment Arbitration Reporter at http://www.iareporter.com/articles/20120207_1)
Claim: USD 700 million (www.globalarbitrationreview.com)
Award: Information not publicly available
Counsel: Volterra Fietta (R. Volterra & S. Fietta) and Latham & Watkins v. Sidley Austin LLP and in-house counsel
Case registered: 27.08.2008
Forum & reference: ICSID Case No. ARB/08/13
Arbitrators: William W. Park (Chair); Marc Lalonde QC; Brigitte Stern
Subject matter: Electricity concession
Status of proceeding: Final Award rendered on 16.07.2012 (attached to the award is a dissenting opinion by arbitrator Marc Lalonde)
Claim: Information not publicly available
Award: Information not publicly available
Counsel: Information not publicly available
Case registered: 2008
Forum & reference: Arbitration Institute of the SCC
Arbitrators: Prof. Gabriele Crespi Reghizzi (Chair); Alexander S. Komarov; Evgeny Kubko
Subject matter: Atomic energy
Status of proceeding: Final award rendered on 28.04.2011
Claim: Information not publicly available
Award: Information not publicly available
Counsel: Mannheimer Swartling LLP (K. Hobér) and Luther Rechtsanwaltsgesellschaft (R. Happ) v. K&L Gates (S. Konrad) and in-house counsel
Case registered: 17.04.2009
Forum & reference: ICSID Case No. ARB/09/6
Arbitrators: Marc Lalonde QC (Chair); Sir Franklin Berman QC; Gabrielle Kaufmann-Kohler
Subject matter: Construction of a coal-fired power plant and environmental protection measures (expropriation)
Status of proceeding: Settled by agreement among the parties embodied in an award by consent dated 11 March 2011
17.09.2009 - The Tribunal holds a first session in Paris
15.03.2010 - Proceeding suspended pursuant to the parties' agreement
27.08.2010 - Suspension of proceeding extended, pursuant to the parties' agreement
11.03.2011 - Parties settle by agreement embodied in an award by consent
Claim: EUR 1.4 billion (globalarbitrationreview.com)
Award: Award (click to download)
Counsel: Shearman & Sterling (Dr. Y. Banifatemi & E. Gaillard) v. Mannheimer Swartling (K. Hobér, J. Ragnwaldh, M. Göransson and T. Pettersson) and BNT (L. Szabó and J. Burmeister)
Case registered: May 2009
Forum & reference: Ad hoc UNCITRAL Arbitration Rules
Arbitrators: Karl-Heinz Böckstiegel (chair); Pierre-Marie Dupuy; Albert Jan van der Berg
Subject matter: Termination of long-term power purchase agreements
Status of proceeding: Pending
Tribunal constituted
Claim: In excess of USD 100 mln
Award: N/A
Counsel: Freshfields Bruckhaus Deringer LLP (W. Plesser, C. Konrad, N. Rubins & J. Commission) v. information not publicly available
Case registered: 03.06.2009
Forum & reference: ICSID Case No. ARB/09/10
Arbitrators: Piero Bernardini (chair); Vaughan Lowe; Francisco Orrego Vicuña
Subject matter: Electricity distribution (expropriation)
Status of proceeding: Settled by agreement among the parties embodied in an award by consent rendered on 2 September 2011
03.06.2009 - Acting Secretary General registers a request for the institution of arbitration proceedings
01.06.2011 - The parties file the full and signed settlement and request the Tribunal to embody their settlement in an award
02.09.2011 - Final award rendered
Claim: Information not publicly available
Award: Information not publicly available
Counsel: Allen & Overy (J. Gill QC, M. Levy & J. Sullivan) v. Reed Smith LLP & 3 Verulam Buildings (B. Paisley; A. Malek QC; C. Harris; A. White QC)
Case registered: 20.07.2010
Forum & reference: ICSID Case No. ARB/10/16
Arbitrators: Pierre Tercier (replacing Gary Born) (Chair); Klaus Michael Sachs; Vaughan Lowe QC
Subject matter: Power facilities and trading companies
Status of proceeding: Pending
05.04.2011 - Tribunal holds first session in London
28.04.2011 - Claimants file a memorial on the merits
07.10.2011 - Respondent files a counter-memorial on the merits
25.06.2012 - Respondents file a rejoinder on the merits
18.07.2012 - Tribunal issues a procedural order concerning the procedural calendar
Claim: Information not publicly available
Award: N/A
Counsel: King & Spalding LLP (K. Fleuriet & R. Smith); Bulboaca & Associates (A. Bulboaca) v. information not publicly available
Case registered: September 2010
Forum & reference: Arbitration Institute of the SCC
Arbitrators: Not yet appointed
Subject matter: Oil fields
Status of proceeding: Pending
Claim: USD 1 billion (globalarbitrationreview.com)
Award: N/A
Counsel: Crowell & Moring LLP (I. Laird, A. de Gramont & A. Riveira) v. Hogan Lovells (M. Davison, L. Gouiffès, M. Burgstaller, T. Kendra)
Case registered: 10.01.2011
Forum & reference: Ad hoc UNCITRAL Arbitration Rules
Arbitrators: David A.R. Williams (Chair); L. Yves Fortier; Bernard Hanotiau
Subject matter: Uranium mining project
Status of proceeding: Pending
Claim: USD 200 million
Award: N/A
Counsel: Hughes Hubbard & Reed LLP (Steve A. Hammond) v. information not publicly available
Case registered: 14.01.2011
Forum & reference: ICSID Case No. ARB/11/2
Arbitrators: Donald M. McRae, Charles N. Brower and Brigitte Stern
Subject matter: Oil exploration and production joint venture
Status of proceeding: Pending
23.04.2012 - Claimant files a memorial on jurisdiction and the merits
15.06.2012 - Respondent files a request to address the objections to jurisdiction as a preliminary question
29.06.2012 - Claimant files observations on the request to address the objections to jurisdiction as a preliminary question
13.07.2012 - Tribunal issues a procedural order concerning Respondent's request to join the objections to jurisdiction to the merits
Claim: Information not publicly available
Award: N/A
Counsel: Allen & Overy (J. Gill QC & J. Sullivan) v. Herbert Smith (E. Soler Tappa & C. Leathley)
Case registered: November 2011
Forum & reference: Ad hoc UNCITRAL Arbitration Rules
Arbitrators: Gabrielle Kaufmann-Kohler (Chair); Judge Charles Brower; Judge Bernardo Sepúlveda-Amor
Subject matter: Retroactive changes to the solar photovoltaic tariff regimes
Status of proceeding: Pending
Claim: Information not publicly available
Award: N/A
The PV Investors is a group of the following 16 investors: AES, Solar, Ampere Equity Fund, Element Power, Eoxis Energy, European Energy, Foresight Group, GreenPower Partners, GWMLux Energia Solar, HgCapital, Hudson Clean Energy, Impax Asset Management, KGAL GmbH & Co., NIBC Infrastructure Partners, Scan Energy and White Owl Capital
Counsel: Freshfields Bruckhaus Deringer v. information not publicly available
Case registered: 05.04.2012
Forum & reference: ICSID Case No. ARB/12/7
Arbitrators: Not yet appointed
Subject matter: Natural gas services
Status of proceeding: Pending
Claim: Information not publicly available
Award: N/A
Counsel: Mannheimer Swartling Advokatbyrå AB, and Luther Rechtsanwaltsgesellschaft mbH v. Ministerium für Wirtschaft und Technologie, and K&L Gates
Case registered: 31.05.2012
Forum & reference: ICSID Case No. ARB/12/12
Arbitrators: Not yet appointed
Subject matter: Nuclear power plant
Status of proceeding: Pending
Claim: Reported in the German media that the claimed damages could exceed EUR 700 mln
Award: N/A